The technology group Wärtsilä will provide an 18 MW extension to the power producing facility and upgrade the electrical and automation system of the present energy plant on the Sabodala-Massawa gold mine advanced in Senegal, West Africa.
The mine is owned by Endeavour Mining, a leading global gold producer. The upgrading and extension challenge will permit for the complete integration of all the site’s power generating capability, whereas making certain the provision of the wanted electric energy to maintain and expand the mine’s manufacturing schedules
he order with Wärtsilä was placed by Sabodala Gold Operations and it has been booked in Wärtsilä’s order consumption in Q3 2022. The challenge might be delivered under a whole engineering, procurement and construction (EPC) contract.
Sabodala-Massawa mine is the biggest producing gold mine in Senegal and is positioned in the jap a part of the nation in the Kedougou region. Endeavour’s deliberate mine expansion will remodel Sabodala-Massawa right into a top-tier gold asset with incremental production.
“Wärtsilä has a depth of experience in delivering energy solutions for mining operations around the world. Not being linked to the grid implies that the captive plant needs to be capable of offering a dependable supply of electrical energy at all times, since no energy equals no production. The Wärtsilä 32 engines selected for this growth challenge have established a powerful popularity for top effectivity and reliability beneath even probably the most difficult ambient situations, eliminating revenue losses from power shortages,” stated Marc Thiriet, Energy Business Director, Africa West, Wärtsilä.
The three Wärtsilä 32 engines to be put in are 20 per cent extra fuel efficient than the plant’s current engines. Their gasoline efficiency minimises the environmental impact by lowering dangerous CO2 emissions. In เกจ์วัดแก๊สหุงต้ม to their outstanding performance, they have the flexibility to support a smooth transition to the combination of solar energy and vitality storage into the system. The upgrade of the electrical and automation system will optimise the interconnection and control for the existing power plant with the extension.
The challenge is predicted to be completed and commissioned before the tip of 2023.
Wärtsilä is Senegal’s main supplier of energy generating tools, and already has 543 MW of installed capability in altogether 20 power crops within the nation. 458 MW of this capability is under Wärtsilä long-term service agreements.